That (A) the budgetary variances set out in paragraph 2.1 of the report be noted;
(B) the following Capital Programme changes be approved:
· ICT Projects – Request for total slippage of £159,160 over various projects. The majority of the outstanding schemes will complete in early 2014/15.
· Footbridge over River Stort - £87,400. Retention payment held pending resolution of contractual issues.
· Heart of Bishop Stortford, Market Improvement Scheme - £45,300. Scheme still in development stage.
· Slippage on various other schemes totalling £42,430 on various other schemes.
· Total slippage into 2014/15 of £334,290.
(C) the controls and scores listed in the strategic risk register for the period January to March 2014, as detailed at paragraph 2.26, be noted.