That (A) the budgetary variances set out in paragraph 2.1 of the report be noted;
(B) £15k of the planning contingency budget being used for joint enforcement manager role, as detailed at paragraph 2.9 of the report, be noted;
(C) the transfer of any underspend in 2013/14 on the priority spend budget to the new homes bonus priority reserve, as detailed at paragraph 2.12 of the report, be supported;
(D) the slippage of £0.777 million of capital schemes to 2014/15 be supported and the budget adjustment for Community Capital Grants, as detailed at paragraphs 2.25 and 2.26 of the report, be agreed; and
(E) £45,000 capital budget for property Investment, as detailed at paragraph 2.27 of the report, be approved.