That (A) the revenue budget forecast overspend of £177k, as detailed at paragraph 2.1 of the report submitted, be noted;
(B) the capital budget forecast underspend of £1.576m, as detailed at paragraph 6.1 of the report submitted, be noted;
(C) the reported performance for the period August 2016 to October 2016, be noted; and
(D) the risk management controls detailed at paragraphs 9.1 to 9.5 of the report be submitted, be approved.
Minutes:
The Executive Member for Finance and Support Services submitted a report on finance, performance and strategic risk monitoring for 2016/17 as at September 2016.
The Executive approved the recommendations now detailed.
RESOLVED - that (A) the revenue budget forecast overspend of £177k, as detailed at paragraph 2.1 of the report submitted, be noted;
(B) the capital budget forecast underspend of £1.576m, as detailed at paragraph 6.1 of the report submitted, be noted;
(C) the reported performance for the period August 2016 to October 2016, be noted; and
(D) the risk management controls detailed at paragraphs 9.1 to 9.5 of the report be submitted, be approved.
Supporting documents: