Decision Maker: Head of Strategic Finance and Property
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Council occupies Buntingford Service
Centre under a lease which is due to expire in 2028. The Service
Centre is used to deliver the waste collection service which
operates under a service contract with an external provider. The
current contract is due to expire in 2025 and work is progressing
to grant a new 8 year contract (with the option for a further 8
years) from this date. The Council therefore needs to extend the
term of the lease to accommodate the length of this contract.
Negotiations have taken place with the Landlord and terms agreed
for a new 15 year reversionary lease effective from November 2028.
The 15 year term will accommodate the duration of a 16 year waste
contract plus an additional 2 years to allow the Council
flexibility should this contract be extended and time to plan for
future arrangements. The lease will contain a day 1 rent review and
thereafter rent reviews every 5 years. Other terms will be broadly
based on the existing lease. The purpose of this report is to seek
authority to enter into this reversionary lease.
The Head of Strategic Finance and Property,
acting under delegated authority under Paragraph 10.13.16 of Part
10 of the Council's Constitution, has decided to grant approval for
the Council to take a new 15 year reversionary lease of Buntingford
Service Centre.
Option 1 - Not Recommended: Allow the existing
lease to expire and move the waste service to an alternative site
but there are currently no other viable sites available for this
use.
Publication date: 08/02/2024
Date of decision: 24/01/2024
Accompanying Documents: