Decision details
Lease of Land to Eclipse Power Networks Ltd for a new electrical transformer sub-station Hartham Leisure Centre, Hertford
Decision Maker: Head of Strategic Finance and Property
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
As part of the redevelopment and refurbishment
of the Hartham Leisure Centre the Council needs to install a new
electrical transformer sub-station and is required and in order to
achieve this is required to grant a lease of the land to the
utility company for 99 years at a rent of £1 per annum. The
installation costs have been previously granted approval as part of
the Hartham Leisure Centre project and the grant of this lease will
not incur any further costs or loss of existing income for the
Council. The Tenant will be responsible for all future liabilities
and outgoings for the site.
Decision:
The Head of Strategic Finance and Property
acting under authority delegated within Section 10, paragraph
10.13.16 of the council’s Constitution 12 May 2022, relating
to the letting of property, has decided to approve the grant of a
lease to Eclipse Power Networks Ltd for a new electrical
transformer substation at Hartham Leisure Centre, Hertford.
Alternative options considered:
None
Publication date: 14/03/2023
Date of decision: 14/03/2023
Accompanying Documents: