Leisure Procurement Update

Meeting: 17/07/2018 - Executive (Item 16.)

16. Leisure Procurement Update pdf icon PDF 46 KB

Additional documents:

Decision:

That (A) the Design and Build aspects of the leisure procurement for Grange Paddocks and Hartham leisure centres are separated from the leisure operating contract, replacing the previously approved “Design, Build, Operate and Maintain (DBOM)” procurement route (recommendations G and H; Council, July2017);

 

(B)     the procurement of the leisure operating contract in parallel to (A) above, be noted; and

 

(C)     the other recommendations from the Council meeting in July 2017 and those agreed in October 2017 remaining the same, be noted.